Construction work of Sayera Khatun Medical College going on in full swing

Dhaka,  Monday,   2016-09-21
Published : 21 Sep 2016, 20:46:30

Construction work of Sayera Khatun Medical College going on in full swing

Our Correspondent


GOPALGANJ, Sept 21: The construction work of Sheikh Sayera Khatun Medical College and Hospital and Nursing Institute is going on in full swing at Teghuria under Sadar Upazila in the district.

Sources from Health Engineering Department (HED) said 65 per cent work of the project has already been completed.

On August 27, 2012, the Health Engineering Dep-artment took possession of 30 acres of land in area. The construction work of the project started on February 25, 2015. MS DUL-PNB (JV), a construction company, took the responsibility to construct the building under the supervision of HED with an estimated cost of Tk 392 million.

Md Ishaque Mia, executive engineer (in-charge) of HED, Gopalganj, said the work is expected to be completed by February 2017.

alimuzzaman81@gmail.com
ADDRESS
Editor : A.H.M Moazzem Hossain
Published by the Editor for International Publications Limited from Tropicana Tower (4th floor), 45, Topkhana Road, GPO Box : 2526 Dhaka- 1000 and printed by him from City Publishing House Ltd., 1 RK Mission Road, Dhaka-1000.
Telephone : PABX : 9553550 (Hunting), 9513814, 7172017 and 7172012 Fax : 880-2-9567049
Email : editor@thefinancialexpress-bd.com, fexpress68@gmail.com
Copyright © 2016. All rights reserved
Powered by : orangebdlogo
close